Oregon has a single state building code. Your city or county enforces it and issues the permit. That split explains most of what confuses homeowners: the rules are statewide, but the counter you go to is local.
Who does what
The state writes the code. The state building code applies uniformly throughout Oregon, and a city or county may not enact different requirements on the same matters unless the Department of Consumer and Business Services authorizes it (ORS 455.040). The Building Codes Division (BCD) adopts the specialty codes and licenses electricians, plumbers and other trades.
Local building departments run permits and inspections. A municipality that takes on a building inspection program administers the state building code for its area (ORS 455.148). BCD's Local Building Department Directory shows which office serves your address. The county building department provides services for most unincorporated areas.
Zoning is separate. BCD tells homeowners to check local land-use (planning and zoning) rules first: "The building code tells you how to construct something while the local laws will tell you if you can construct something" (BCD, About Oregon residential building permits).
The codes in effect now
Two residential code editions overlap right now, so dates matter (BCD Adopted Codes):
| Code | Edition and dates |
|---|---|
| Oregon Residential Specialty Code (ORSC) | 2026 ORSC: chapter 1 effective and mandatory October 1, 2026; chapters 2 to 44 effective October 1, 2026 and mandatory April 1, 2027. BCD still lists the 2023 ORSC alongside it. |
| Oregon Electrical Specialty Code (OESC) | 2026 OESC, effective October 1, 2026, based on the 2026 National Electrical Code |
| Oregon Plumbing Specialty Code (OPSC) | 2026 OPSC, effective October 1, 2026, based on the 2024 Uniform Plumbing Code |
| Oregon Mechanical Specialty Code (OMSC) | 2025 OMSC, effective October 1, 2025, mandatory April 1, 2026 |
If your project was designed before October 2026, ask your building department which ORSC edition it will be reviewed under.
Work that needs a permit
BCD's homeowner guidance applies to detached one- and two-family dwellings (BCD, About Oregon residential building permits). Permits are required for all new construction and for structural, plumbing, mechanical and electrical changes. BCD's examples:
Building (structural)
- Adding a room
- Building or moving a carport, garage or shed of more than 200 square feet
- Adding, moving or removing walls
- Finishing an attic, garage or basement into living space
- Cutting a new window or door opening, or changing the size of an existing one
- Re-roofing when all the old roofing is removed and all new sheathing is installed
- A deck, or stairs to the primary door, porch or deck, more than 30 inches above grade
- A fence that serves as a barrier around a pool, hot tub or spa
Electrical
- Installing or altering permanent wiring or electrical devices
- New or upgraded outlets or light fixtures, a garage-door opener receptacle, converting a fuse box to breakers
- Installing or altering low-voltage systems such as security alarms
Plumbing
- Replacing a water heater (a plumbing contractor may use a minor label permit)
- Altering piping inside a wall, ceiling or under a floor, and all new plumbing
- Emergency repair of freeze-damaged or leaking concealed piping when the new piping exceeds five feet
- Relocating plumbing in a remodel, including building sewers, water service and rain drains connected to the sewer
Mechanical
- Heating or cooling equipment vented into a chimney
- Wood stoves, fireplace inserts, pellet stoves and their venting
- Gas piping between the meter or LPG tank and an appliance
- Bath fans, dryer exhausts, kitchen range exhausts and other vented appliances
BCD adds that the State Fire Marshal requires anyone, including homeowners, who installs, extends, alters or repairs an LP gas appliance or piping, vent or flue connection to be licensed through the Fire Marshal.
Work that usually doesn't need a building permit
From BCD's list of residential exemptions:
- A detached, nonhabitable, one-story accessory structure under 200 square feet and under 15 feet from floor to average roof height
- A patio, porch or deck cover no more than 200 square feet and 12 feet average roof height, at least 3 feet from any property line
- A porch or deck no more than 30 inches above adjacent grade at any point
- A wood, wire mesh or chain link fence under 7 feet tall
- A concrete sidewalk, slab or driveway no more than 30 inches above grade and not over a basement
- Paint, wallpaper, tile, carpet, cabinets, countertops and similar finish work
- Nonbearing interior walls, unless they create a habitable room, a toilet room or a bathroom
- Siding repair or replacement where fire resistance isn't required
- Insulation, masonry repair, gutters and downspouts
- Replacing doors and windows with no structural change
- Replacing roofing that weighs no more than 30 percent of the roof's required live load design capacity, where fire resistance isn't required
- Like-for-like repairs that don't cut a wall, remove or cut a beam or load-bearing support, or affect required exits
BCD warns that work exempt from a building permit may still need an electrical, plumbing or mechanical permit, and that work not meeting every condition of an exemption needs a permit. When in doubt, call your local building department.
Permit timing
A permit expires if work doesn't begin within 180 days of issuance, or if work stops for 180 days or more. Ask the building official for an extension if you need one. The permit, and any approved plans, must be on site for the inspector (BCD).
Permits and your contractor
BCD says the person performing the work is responsible for obtaining the permits. For a contractor, the permit office must collect a signed statement with the CCB license number, may not issue a permit to someone required to be licensed who isn't, and lists the license number on the permit (ORS 701.325(1)). A contractor who works without a required building, electrical, mechanical or plumbing permit, and draws a CCB complaint, can be disciplined (ORS 701.098(1)(j)).
A contractor who asks you to pull the permit in your name is asking you to take on the owner-builder duties described in who needs a CCB license. Ask why.
Related pages
- Electrical license and permit rules
- Plumbing license and permit rules
- Oregon contractor licensing guide
- Find roofers, fence contractors and concrete contractors near you
Sources
- BCD: About Oregon residential building permits
- BCD: Adopted codes online
- BCD: Local Building Department Directory
- ORS 455.040, 455.148
- ORS 701.098, 701.325 (2025 edition)
Frequently Asked Questions
Who gets the building permit in Oregon, me or the contractor?
The person doing the work, whether homeowner or contractor, is responsible for getting the permits (Building Codes Division). A city, county or state agency may not issue a permit to someone who is required to have a CCB license and doesn't, and it lists the contractor's license number on the permit (ORS 701.325).
Do I need a permit to replace my roof in Oregon?
It depends on the scope. Building Codes Division lists re-roofing as permit-required when all the old roofing is removed and all new sheathing is installed. Replacing roofing is exempt when the replacement weighs no more than 30 percent of the roof's required live load design capacity and the roof isn't required to be fire resistant.
Do I need a permit to replace a water heater in Oregon?
Yes. Building Codes Division lists water heater replacement as permit-required work. A licensed plumbing contractor may use a minor label permit for it.
How long is an Oregon building permit good for?
A permit expires if work doesn't start within 180 days of issuance, or if work is suspended or abandoned for 180 days or more after it starts. You can ask the local building official for an extension (Building Codes Division).